LIPA's state-imposed fees to jump as high as 380% to cover big-ticket projects

A view of the property for a proposed substation that's part of the Propel NY Energy cable project on Shore Road in Glenwood Landing. Credit: Newsday/J. Conrad Williams Jr.
Long Islanders' share of the cost to cover New York’s plans for large-scale energy storage plants will jump more than 300% over the next four years, from 17 cents a month this year to 70 cents by 2030, according to recent state estimates.
Estimates also show the cost for new transmission lines such as Propel NY Energy and others will jump 380% to $4.71 from 98 cents during that time.
The new estimates, released in a comprehensive report by the state Department of Public Service, are aimed at disclosing to ratepayers the real cost of grid upgrades tied to the state climate act of 2019.
The anticipated increase in the cost of energy storage plants over four years comes despite widespread moratoriums declared across Long Island and a recent stance by Brookhaven Town that it’s in "no rush" to approve any such projects.
WHAT NEWSDAY FOUND
- Long Islanders' costs for energy storage and transmission upgrades are projected to increase by 2030, with energy storage costs rising over 300% and transmission costs increasing by 380%.
- A state Department of Public Service report highlights these cost increases as part of grid upgrades linked to the 2019 state climate act, despite local resistance due to safety concerns from lithium-ion battery fires.
- Commercial and industrial users on Long Island will face even higher cost increases.
Much of the concern is rooted in fires at lithium-ion battery plants that occurred in four locations across the state in 2023. Among them was a fire in East Hampton, where the state is investigating a toxic plume suspected of being caused by the plant's internal fire extinguishment system.
The DPS emphasized the projected costs "do not reflect estimates of potential offsetting savings or the impact of other potential benefits such as increased utility revenues that may reduce the need for future rate increases."
Actual estimates
The state cost estimates, which are updated each year by the DPS, may be higher for most Long Islanders than reported.
That’s because the state’s figures for LIPA/PSEG customers are based on monthly usage of 600 kilowatt hours. Actual usage by LIPA’s residential customers averages closer to 750 kilowatt hours a month. The DPS included the 600 kwh figure to have an apples-to-apples comparison across all state utilities.
The state also projects increases in the cost of mandates that are partly tied to Long Island’s existing contract for the South Fork Wind Farm. The monthly impact of clean-energy standard costs per month is estimated at $6.80. It’s projected to drop next year to $5.85, then increase to $7.62 a month by 2030, according to estimates.
Overall, Long Islanders' electric bills over the study period will jump from an average $175.16 this year to $192.91 by 2030, based on the climate-related upgrades, although Long Islanders are likely to pay more. Just last month, LIPA’s projection for actual bills this year was $221.05 a month, while next year could range from $206.18 a month to $237.97.
Where's the money going?
In response to Newsday's questions, DPS spokeswoman Kim Mashke said in a written statement LIPA’s various energy projects under its so-called "feed-in tariffs" program — which pays outside developers fees for green energy produced for the grid, including certain solar energy projects — are represented in the clean-energy standard cost, as is the South Fork Wind Farm.
She said the cost for the two programs couldn’t be broken out. LIPA in the past has said the South Fork Wind Farm would cost average customers around $1.60 a month, Newsday has reported.
Energy storage is another driver of the cost, and it's tied to the New York State Energy and Research Development Authority's plans to have dozens of utility-scale battery plants and other storage facilities operating by 2030. Mashke said the 70 cents by 2030 assumes 1,500 megawatts of energy storage already under contract is operational by then. To date, there's less than 15 megawatts of bulk-energy storage on Long Island, but the state has been awarding contracts for large projects in recent months, including one in Holtsville and another in Manorville.
Mashke said the Propel project represents 34% of the monthly $2.76 fee projected for residential LIPA customers by 2029 to cover transmission upgrades. It represents 39% of the $4.71 per-month fee forecast for 2030, she said.
That means Long Island customers who use 600 megawatts of power each month will be paying $1.83 a month for Propel when it’s scheduled to be online in 2030.
For those who use a more typical 750 kwh a month, the cost would be closer to $2.30 per month, according to Newsday calculations.
Commercial vs. Industrial users
For commercial users on Long Island, the costs during the next four years are higher.
The clean-energy standard costs for commercial accounts using 12,600 kilowatts per month will be $3.55 for the battery program this year, and will increase to $14.64 by 2030. The cost for transmission lines, including Propel, jumps from $20.66 to $99 a month by 2030, and the clean-energy standard costs go from $142.84 a month this year to $160.11 by 2030.
For bigger industrial entities using 720,000 kilowatt-hours a month, the clean-energy standard contribution increases from $8,162.44 a month this year to $9,148.98 by 2030, while the bulk storage cost increases from $203.02 to $863.57 a month. Transmission upgrades would cost that industrial customer $1,180.85 a month this year and jump to $5,657.41 by 2030.
Newsday has requested updated cost estimates for the Propel cable line, which developers in 2023 estimated at $3.26 billion. Susan Craig, spokeswoman for the New York Power Authority, said $3.26 billion remains the working estimate. But she noted the authority had not begun construction yet (it was delayed this month to early next year) and was still negotiating certain contracts.
Propel last week announced a list of construction firms that will work on the project, including Melville-based Haugland Group, and also said it would delay the start of construction to early 2027. The project still awaits a final permit from the U.S. Army Corps of Engineers, which has not returned calls seeking comment.
Craig said Propel NY is "currently projected to save Long Island ratepayers nearly $5.9 billion over the first 20 years" by alleviating congestion on power transmission lines, as well as "local capacity requirement related costs."
Thousands of North Shore residents, six school districts, the Village of Sea Cliff and U.S. Rep. Tom Suozzi, among others, have expressed opposition to the plan to construct the 90-mile Propel cable, citing impacts on Hempstead Harbor, traffic and businesses.

Loading video…
From new traditions to old: NewsdayTV's Thanksgiving special From Thanksgiving gatherings to unique baked goods to holiday shopping, Newsday is taking a look at how Long Islanders are celebrating Thanksgiving.

Loading video…
From new traditions to old: NewsdayTV's Thanksgiving special From Thanksgiving gatherings to unique baked goods to holiday shopping, Newsday is taking a look at how Long Islanders are celebrating Thanksgiving.