Anticipated arrival of more offshore wind energy poses new challenges for LIPA

Wind turbines in the Atlantic Ocean for the Sunrise Wind project about 35 miles off the coast of Montauk are seen on Oct. 3. Credit: Newsday/Steve Pfost
A large-scale injection of offshore wind energy to Long Island, starting with a trickle next month, presents new opportunities and new challenges for managing the electric grid, as battery plants to store excess power remain stalled and wind production is highest when it’s needed least.
LIPA says the grid and its managers at PSEG are up to the challenge, aided not only by two years of experience overseeing the strong, but intermittent production cycles of the smaller South Fork Wind Farm, but their longer-term ability to balance the increasingly diverse energy sources that now make up the grid.
At full capacity, Sunrise Wind will be one of the largest power sources to Long Island, second only to the Northport power station. (Northport delivers just over 1,500 megawatts compared with Sunrise's 924 megawatts.) The question for the Long Island Power Authority: what will happen on cold winter nights when wind production is highest and demand lowest?
"There’s room for wind," said Gary Stephenson, senior vice president of power supply at LIPA, explaining that clean new power will displace some fossil-fuel energy production.
WHAT NEWSDAY FOUND
- As an injection of offshore wind energy arrives on Long Island, LIPA faces new challenges for managing the electric grid, as battery plants to store excess power remain stalled and wind production is highest when it’s needed least.
- LIPA says the grid and its managers at PSEG are up to the challenge, as Sunrise Wind begins to deliver energy. At full capacity, Sunrise will be one of the largest power sources to Long Island,
- The question for the LIPA: What will happen on cold winter nights when wind production is highest and demand lowest.
What’s more, Stephenson said, the prospect of hundreds of megawatts of cheaper wind energy is projected to help bring down wholesale market prices.
At times of peak wind production, "We’d turn down the fossil units to their minimums," Stephenson said. Even old plants like Northport have a "pretty good range of minimum to maximum so the system operator will put most of those at minimum and allow the wind because it’s the cheapest" energy, he said. Some gas plants may be turned off completely when the wind is highest.
The first energy from the Sunrise Wind farm’s 84 turbines is expected to reach the Long Island grid at Holtsville beginning in December, developer Orsted said in responses to Newsday.
"Turbine installation remains underway at Sunrise Wind along with commissioning work at the offshore converter station," spokeswoman Meaghan Wims said of the project off the coast of New England, adjacent to South Fork. Completion of the $7 billion, 924-megawatt project, which promises to power up to 600,000 homes, or around half of LIPA’s total customer base, is still on target for the second half of 2027. More than a third of the 84 turbines have been fully installed.
Orsted declined to answer any of Newsday’s questions about how the developer expects to maximize its investment given that there are no new big battery storage plants around the facility's receiver station in Holbrook, as had been envisioned. Most of Long Island has moratoriums on battery plants and even Brookhaven has said it is in "no rush" to approve them. Nor would Orsted say what it would do to prevent "curtailment," a practice of literally putting the brakes on wind turbines when they are producing more energy than the system needs or can handle.
"We will decline to comment," Wims wrote.
The state Public Service Commission, in recent responses to Newsday, said a separate transmission project originally proposed to export excess wind energy from the waters off Long Island to the upstate grid could benefit from Sunrise. The 90-mile, 3,000-megawatt transmission project known as Propel NY Energy isn't expected to be operational until 2030.
"Once Propel NY is operational, the power provided by Sunrise can more easily be transferred to the area of highest demand within these downstate load zones, and if needed, out of these downstate load zones," PSC spokeswoman Kim Mashke wrote.
'Inadequate transmission capacity'
But the idea of sending the power to the west to hook up to Propel may also prove challenging because of somewhat limited transmission backbone that connects eastern Suffolk to more concentrated loads to the west, experts say. At present LIPA’s backbone is served by a series of 138,000-volt power connections. Most of Propel’s 3,000 megawatts is via 345,000-volt cables. The most eastern leg of Propel, a 345,000-volt substation at Ruland Road in Melville, is 24 miles from Sunrise's substation in Holbrook, which is connected by lower-capacity 138,000-volt transmission lines.
Four years ago, the agency charged with overseeing state energy markets in an annual review foresaw a future in which large amounts of wind power then headed for Long Island came up against a grid that had "inadequate transmission capacity."
As the New York Independent System Operator saw it, the state grid faced the prospect of increasingly large amounts of "curtailment," the practice of ceasing renewable energy generation because the grid would be flooded with new intermittent energy atop existing fossil and hydropower generation.
Four years later, most of the projects planned at the time — more than 4,000 megawatts of offshore wind — have been canceled or withdrawn. Only two projects, Sunrise and Empire Wind, remain.
When LIPA was considering plans for a big new power plant in Brookhaven in 2001, it also conducted a study of the Holtsville constraint, and determined that a certain amount of power would be "bottled" by the transmission system.
"This 'bottling' phenomenon will prohibit that amount of generation from exiting across the Holbrook interface to serve load in the remainder of Long Island," the study found.
Asked last week whether there’s a need for a bigger transmission pipeline from Holbrook to Melville to accommodate Sunrise Wind power, a spokesman for the NYISO said its reliability studies "account for Sunrise Wind and the evolving generation and transmission system." He pointed to recent studies that indicate a need for Propel, but didn’t respond to inquiries about a possible need for a bigger backbone east to connect to Propel’s starting point in Melville.
LIPA’s grid has continually been upgraded since 2001, including to accommodate Caithness and South Fork Wind. As a result, said Stephenson, he does not expect curtailment to be a factor for Sunrise Wind. "We don’t see a lot of constraints right now," he said.
LIPA’s East End is fed by up to 130 megawatts of offshore wind energy by the South Fork Wind Farm, making enough energy to feed the power-constrained Hamptons in the offseason. LIPA, whose summer peak power of more than 5,000 megawatts roughly halves on cold winter nights, also has plenty of power from the 350-megawatt Brookhaven Energy Center, which combined with other fossil-fuel generators from National Grid has kept the central Suffolk section of the grid in plenty of power.
Stephenson said while engineers do face new challenges as they work to integrate that new infusion of wind-energy from Sunrise onto the grid, it’s a challenge with plenty of flexibility, and upside.
State utilities help offset wind costs
Utilities across the state will collectively subsidize part of the cost for energy from Sunrise Wind through the purchase of state-mandated offshore wind renewable energy credits. Sunrise gets a guaranteed minimum price for the power ($146 per megawatt hour), even if the wholesale price is lower, paid for through those so-called ORECs.
But even as that power makes its way to Long Island, LIPA has yet to agree to that OREC pricing scheme mandated of other state utilities, said the PSC’s Mashke. Ratepayers of six other utilities across the state will pay an average $2.56 per month for those credits from Sunrise and Empire wind farms but the cost "does not apply to LIPA consumers," Mashke said.
LIPA spokeswoman Michelle Livingston explained that LIPA customers "already support offshore wind through our long-term agreement with South Fork Wind, which includes electricity and renewable energy credits. Participation in the statewide program is under review."
Stephenson said that under "most circumstances" he does not expect LIPA to have to curtail wind-energy production from Sunrise based on the transmission limitations between Holtsville and Melville — at least not now. It could become an issue, as the NYISO foresaw, when larger amounts come onto the grid — an equation anticipated by Propel.
"There’s only so much wind we can consume," Stephenson said. "Our load in the middle of the winter is only a couple of thousand megawatts." Under current constraints "we can’t absorb 3,000 megawatts of wind, plus South Fork."
One of the answers to the problem is to build more battery storage plants, a prospect that has drawn community opposition on Long Island. The state has issued solicitations for thousands of megawatts of energy storage with plans for some 6,000 megawatts by 2030.
"This bottleneck could significantly have been avoided if, in fact, there was greater success for the battery energy storage rollout, especially at the Holbrook interface," said William J. Miller, a longtime energy expert at the Clearview Consultants familiar with the Melville to Holbrook challenge.
"With more wind we’ll definitely need more batteries, there’s no doubt about it," Stephenson said. "They make sense now, they tend to be the cheapest on an upfront cost basis."
Challenges aren't insurmountable
LIPA has also had the experience of integrating the South Fork onto the grid, a complex operation that has gone smoothly to date.
"We’ve had a year or so of dealing with the ups and downs of South Fork and its 132 megawatts," Stephenson said. "Now we have this new array that’s eight times as big in the same spot in the ocean, so its characteristics are going to look the same. We’ve got good experience. We’re moving from the minor leagues to the major leagues with Sunrise." That influx is "going to put a lot of stress on system operations as they deal with that."
Another challenge is forecasting for natural gas usage to augment the wind power.
"If we think tomorrow that we’re going to get 1,000 megawatts of wind, and it doesn’t show up, well guess what? We’re pulling gas," Stephenson said. "And where does that gas come from? So it’s not just electric, it’s also that gas side that’s got to be ready to respond."
Observers say the issues are far from insurmountable, and may present opportunities.
Billy Haugland, CEO of the Haugland Group of Melville, which built Sunrise Wind's 17-mile land based transmission line from Smith Point to Holtsville for Sunrise, and was recently named a contractor to help construct Propel, said an ideal match for Sunrise Wind would be to build a 345,000-volt power line from Holbrook to Melville, where Propel will have its easternmost point.
While it may not be on the drawing board now, Haugland said such a 345,000-volt extension could be completed with state and local cooperation using Long Island Expressway service roads rather than through neighborhoods.
Robert Catell, chairman of the Advanced Energy Research and Technology Center at Stony Brook University and former CEO of KeySpan and National Grid, said he was confident that the grid will keep up with wind production and adapt as needed.
"That wind power is going to be absorbed on Long Island and the gas plants won’t run as much," Catell said.
But there are challenges. "The wind doesn’t always blow," he noted, so LIPA may need shorter-term solutions to keep the lights on, including peaker plants. Catell said he believes more wind power, including projects previously canceled, could be revived over time and that the region needs to be ready. He has backed Propel.
Paul DeCotis, senior partner in the energy and utility practice at consulting firm West Monroe and a former LIPA vice president of power markets, said batteries will be the real key to maximizing any excess power.
"To have a cleaner grid with more solar and wind and non-emitting resources, you need storage," DeCotis said, adding that the value of utility-scale storage is "underestimated in the public mind."
Loading video…
Holiday forecast: When will the worst of weather arrive? ... Travel woes for Thanksgiving ... Can't cook? These restaurants are open ... Why veteran, 103, is giving thanks
Loading video…
Holiday forecast: When will the worst of weather arrive? ... Travel woes for Thanksgiving ... Can't cook? These restaurants are open ... Why veteran, 103, is giving thanks